Electricity to the New Quay

Nov 12th, 2009 by j.k | 0

Yesterday the electrcity supply was connected to the new quay and the landing lights were tested.

Deck Slabs

Nov 12th, 2009 by j.k | 0

The new quay is substantially complete.  Work continues on the new deck structure which will connect the new berths to the  landside facilities.

Central deck slabs

Sep 22nd, 2009 by t.w | 0

The casting of the central deck slabs has begun.

North End

Sep 8th, 2009 by t.w | 0

View of the North end complete with timber fendering.

West landings

Sep 2nd, 2009 by t.w | 0

Internal staircases and landings on the west side under construction.