Last Concrete Pour

Dec 15th, 2009 by j.k | 0

Geomarine poured the last concrete slab today under the current phase of the project

The fencing, which will be installed on Thursday, is the last item to be completed before the Harbourmaster takes over the new facility in January 2010.