Archive for 'Notes from the quay' Category

First Large Double Berthing

Aug 2nd, 2010 by admin | 0

For the first time, two large container vessels have been able to berth simultaneously at Alderney.
More info on the IFC website.

Read full post...

New freight service started

Mar 2nd, 2010 by s.g | 0

The quay is now being used for a new freight service provided by Huelin Renouf, a video of the MV Huelin Dispatch using the quay is available at the Gurnsey News Channel Online website.

Read full post...

New Cargo Service

Jan 25th, 2010 by j.k | 0

The enlargement of the commercial quay means that it can now accomonmdate larger cargo vessels.  On Saturday, the Huelin Dispatch carried out a successful berthing trial and became the largest vessel to tie up alongside in Alderney.

Read full post...

Last Concrete Pour

Dec 15th, 2009 by j.k | 0

Geomarine poured the last concrete slab today under the current phase of the project

The fencing, which will be installed on Thursday, is the last item to be completed before the Harbourmaster takes over the new facility in January 2010.

Read full post...

View of phase 1 and 2

Dec 2nd, 2009 by t.w | 0

View of the new quay (phase 1) and phase 2 slab work which is still under construction.

Read full post...