New Cargo Service

Jan 25th, 2010 by j.k | 0

The enlargement of the commercial quay means that it can now accomonmdate larger cargo vessels.  On Saturday, the Huelin Dispatch carried out a successful berthing trial and became the largest vessel to tie up alongside in Alderney.

Last Concrete Pour

Dec 15th, 2009 by j.k | 0

Geomarine poured the last concrete slab today under the current phase of the project

The fencing, which will be installed on Thursday, is the last item to be completed before the Harbourmaster takes over the new facility in January 2010.

View of phase 1 and 2

Dec 2nd, 2009 by t.w | 0

View of the new quay (phase 1) and phase 2 slab work which is still under construction.

Electricity to the New Quay

Nov 12th, 2009 by j.k | 0

Yesterday the electrcity supply was connected to the new quay and the landing lights were tested.

Deck Slabs

Nov 12th, 2009 by j.k | 0

The new quay is substantially complete.  Work continues on the new deck structure which will connect the new berths to the  landside facilities.